On 15 November 2018, the celebration took place in the new kiln house on the premises of 3M in Villach, together with a hearty carpenter’s speech.

To date, approx. 1,800m3 of concrete has been delivered with over 250 concrete mixing vehicles and 95,000kg of steel has been processed.
Thanks to the professional cooperation and the “Safety-First-Initiative” between the construction company Porr, the client 3M and the company Lorenz Consult, the new building was erected in a record time of only 12 weeks without any accidents.