Some interesting facts about the completed surgery shell.

  • 395 – Total construction plans
  • 209 – Formwork plans
  • 186 – Reinforcement plans
  • 788 tons = 788000 kg of reinforcing steel
  • 5300 m³ concrete = approx. 705 mixer wagons/ truckloads
  • Start of construction shell to shell finished = 11 months
  • 107,5 GB project data
  • 3D model with 17581 elements